Timeline | DRAFT | |||||||||||
| 11/21/2006 | Draft RFP ready for internal review including governance and/or steering committee | ||||||||||||
| 12/10/2006 | Community review | ||||||||||||
| January | Issue RFP | ||||||||||||
| 02/07/2007 | RFP opening | ||||||||||||
| 2/22/07 to | |||||||||||||
| 02/28/2007 | RFP review and consultant presentations | ||||||||||||
| 2/28/07 to | |||||||||||||
| 03/08/2007 | Prepare contract | ||||||||||||
| 3/9/07 to | |||||||||||||
| 03/15/2007 | Review by County offices (PDS, PA, AS, Executive) | ||||||||||||
| 03/16/2007 | Contract to Executive Office for inclusion in Council packet | ||||||||||||
| 03/27/2007 | Council action | ||||||||||||
| 4/1/07 to | |||||||||||||
| 08/31/2007 | Contract performance period | ||||||||||||
| 07-Sep | Report complete | ||||||||||||